- Get Pre-Qualified
 - Choose your floor plan and lot
 - Write purchase contract
 - Apply for financing
 - Plan Review
Sign off on blueprints
10% deposit due (Deposit will be applied toward down payment due at closing) - Personalized Color Selection
 - Plot Plan applied for
 - Sign off on Plot Plan (approximately 1 business week from blueprint sign-off)
 - Apply for building permit (approximately 3-5 weeks after plot plan is signed)
 - Finalize color Selection
 - Permit issued and building begins
 - Select Appliances (Upgrade Only) at Custom Distributors
 - Select Flooring at Classic Carpet
 - Select Lighting at Ferguson
 - Pre-Closing walkthrough (A few days prior to closing)
 - Closing (Approximately 180 days after permit is received)